The word frightens boards more than it should, and the reason is a picture most people carry of what it involves: the whole building open at once, residents in hotels, months of noise, a special assessment nobody saw coming.
That is one way to repipe a building. It is rarely the way an occupied condominium is actually done.
The unit of work is the line, not the building
An occupied building is repiped by stack. One vertical line at a time, with the units on it, closed out before the next one starts.
What that means practically is that the disruption is narrow and moving. If your building has eight lines, roughly an eighth of the residents are affected at any point, and the other seven eighths are living normally and mostly wondering what the vans are for.
It also means the project has a rhythm a board can report against. Phase three of eight complete, two units deferred for access, on schedule for the next. That is a thing you can put in a newsletter. “The repipe is ongoing” is not.
What has to be decided before anybody is priced
The expensive decisions in a repipe are made before a single pipe is touched, and they are board decisions rather than trade ones.
Supply, waste, or both. These fail on different clocks. Galvanized supply closes up from the inside and announces itself through pressure. Cast-iron waste fails from the inside out and announces itself through leaks and smell. A building can genuinely need one and not the other, and the survey should say so rather than quoting both because both is a bigger job.
Where the association’s responsibility stops. The declaration decides this and it decides who pays. It has to be settled before pricing, because a scope that is ambiguous about the branch connection is a scope that produces an argument in month three.
What happens to finishes. Reinstatement is most of what owners judge the job on and most of where scopes go vague. Who patches, to what standard, painted or not, tiled or not, matched how. A quote that says “make good” without defining it is not a quote.
All at once or over years. Addressed in the questions above; the point is that it is a funding decision with a known cost difference, and it should be made against both numbers.